DHA Lahore Building Control Procedures – Step-by-Step Guide for Residents and Investors
The Defence Housing Authority (DHA) Lahore is one of Pakistan’s most trusted and prestigious residential authorities. For residents, investors, and builders, adhering to DHA building control procedures is essential for smooth construction, legal compliance, and avoiding fines.
This comprehensive guide explains the core procedures, advisory notices, required documents, processing timelines, and bylaw compliance for all under-construction buildings in DHA Lahore. Whether you are building a new home, renovating an existing property, or installing solar systems, this guide covers everything you need to know.
⸻
1. Core Advisory for All Under-Construction Buildings
DHA Lahore emphasizes transparency, safety, and anti-corruption measures at construction sites. Residents and contractors must ensure:
• Verify DHA Building Control Staff ID: Always check staff identity before inspections.
• No Cash Payments: All dues must be paid through DHA-issued vouchers via banks.
• Coordination with Professionals: Work with your enlisted Architect and Structural Engineer for all construction activities.
• Report Malpractice: Any suspicious activity or malpractice attempts should be reported immediately to DHA authorities.
• Support Desk: For queries, visit the Building Control Help Desk or contact UAN: 042-111-342-547 or email cad.bc@dhalahore.org.
Motto: “TOGETHER WE SAY NO TO CORRUPTION.”
⸻
2. Other Key Permissions & Procedures
DHA Lahore Building Control oversees a variety of construction-related approvals, including:
• Revised Drawings Approval
• Temporary Sewerage Connection
• Neighbor Complaints
• Amalgamation or Subdivision of Plots/Buildings
• Permission for Use of Plot as Lawn
• Renovation Approvals
• Crane Usage Permission
• Demolition of Existing Buildings
• Solar Installation / Validation
• No Demand Certificate for Property Transfer
Note: Specimen forms and undertakings are available at DHA Main Office Complex, Public Relations Branch. Email: ad.bc@dhalahore.org.
⸻
3. Step-by-Step DHA Building Control Procedures
Step 1: Site Plan Approval
Required Documents:
• Crane Forms (2 Copies)
• Copy of CNIC (Owner or Power of Attorney Holder)
• Copy of Allotment Letter
Processing Time:
• Normal: Phase 1-7 & 9 → 7 working days; Phase 8, 11 & 12 → 11 working days
• Executive: Phase 1-7 & 9 → 2 working days; Phase 8, 11 & 12 → 3 working days
Additional Notes:
• Charges payable at time of application
• Clear any outstanding dues (development dues, excess area charges, NUF)
⸻
Step 2: Drawing Submission & Approval
Required Documents:
• 2 x Tracing Cloth Prints
• MEP & Fire/Safety Drawings (2 x Ammonis Prints)
• Certificates: Electrical, Mechanical, Architect Stability, Structure Stability
• Owner Documents: CNIC, Allotment/Transfer Letter, Site Plan
• Paid Challan: Drawing Scrutiny/Vetting Charges
• Soft Copy: AutoCAD File (CD)
• Geotechnical Report (Valid 1 Year)
• Architect Signatures and Approvals
Processing Time:
• Normal Application: 20 working days
• Executive Application: 5 working days
Validity: 2 years
⸻
Step 3: Demarcation of Plot
Required Documents:
• NOC for dues clearance from DHA Finance
• Demarcation & Inspection Sheet
• Undertakings: Stacking Material & Temporary Hut (E-Stamp)
• Approval Letter Copy of DHA Drawing Approval
• Paid Challan for Possession Charges
Additional for Basement:
• Method of Construction
• Undertaking for Machinery (E-Stamp)
• Refundable Security: Challan & Undertaking (E-Stamp)
Processing Time:
• Normal: 7 working days
• Executive: 2 working days
Validity: 1 month (if construction not started)
⸻
Step 4: Construction Period (2 Years)
Requirements During Construction:
• Engage professional Architect and Structural Engineer
• Structure stability must be maintained and documented on Demarcation & Inspection Sheet
• Any revised drawings or changes require prior approval
• Construction must comply with DHA approved bylaws to avoid fines
• Septic tank and lavatory must be constructed within plot area before water/sewer connection application
• Completion certificate must be obtained within 5 years of drawing approval
⸻
Step 5: New Water & Sewerage Connection
Required Documents:
• Filled application form (Owner/Attorney)
• Paid Challan (Original + 1 Copy)
• CNIC Copy of Owner/Attorney
• Site Plan Copy
• For Solar System Owners:
• LESCO Meter Permission/Electricity Bill
• Licensed Solar Installer Copy
• Solar Panels Stability Certificate
Processing Time: 21 working days
⸻
Step 6: Completion Certificate Application
Required Documents:
• Application on plain paper addressed to Executive UNO / Building Control
• 2 x photographs (front & elevation, 6”x4”)
• 2 x approved architectural drawings
• Paid Challan for Completion Certificate
• Additional fees if applicable (e.g., sewer tampering)
• Owner’s documents: CNIC or Power of Attorney
Processing Time:
• Normal: 21 working days
• Executive: 5 working days
⸻
4. Key Notes for DHA Residents
• Always verify staff cards and credentials during inspections
• Use approved professionals (Architects, Structural Engineers, Solar Vendors)
• Clear all dues before applying for permissions or connections
• Follow DHA bylaws strictly to avoid penalties or delays
• Maintain proper documentation for all construction stages
⸻
5. Why Following DHA Procedures Matters
• Ensures legal compliance and avoids fines
• Protects structural integrity of your property
• Enables timely approval for utilities like water, sewer, and electricity
• Supports safe and sustainable construction practices
• Maximizes investment value and resale potential
⸻
6. About Islam-Estate® – Your DHA Real Estate Expert
Islam-Estate® is an authorized DHA property company providing:
• Expert guidance on DHA building control procedures
• Assistance in site plan approvals, drawings, demarcation, and completion certificates
• Support for solar system installation and DHA bylaw compliance
• Verified DHA residential and commercial property listings
📞 Contact Faraz Shoukat at 0321-4000646 for DHA property guidance, building control procedures, solar system approvals, and residential or commercial property solutions. Visit DhaRealEstate.pk for details.
⸻
Key Highlights
• Construction Period: 2 years (from drawing approval)
• Water/Sewerage Connection: Requires approved documents and paid challan
• Completion Certificate: Mandatory for final possession
• Solar System Installation: Requires DHA approval and licensed vendors
• Core Principle: Follow DHA bylaws, avoid corruption, and ensure safety
⸻
DHA Lahore, DHA building control procedures, DHA construction guidelines, DHA site plan approval, DHA drawing approval, DHA demarcation, DHA completion certificate, DHA water and sewer connection, DHA solar installation, DHA bylaw compliance, DHA residential plots, DHA commercial plots, DHA property investment, Islam-Estate DHA, buy DHA plots Lahore, DHA legal construction, DHA Pakistan real estate.